Ethiopia - University Capacity Building Program International Projects
Location: Ethiopia - University Capacity Building Program
Planning: 2007 - 2008
Program: University Capacity Building Program (UCBP) -
GTZ-IS
Wastewater treatment plant for 7,000 - 14,000 PE;
Preliminary Design
- Treatment of the wastewater by sand traps, anaerobic reactors (UASB) or Trickling Filters and root zone
treatment plants
- Biogas storage and use
- Reuse of treated wastewater for irrigation
Planning: 2007 - 2008
Program: University Capacity Building Program (UCBP) -
GTZ-IS
Wastewater treatment plant for 7,000 - 14,000 PE;
Preliminary Design
- Treatment of the wastewater by sand traps, anaerobic reactors (UASB) or Trickling Filters and root zone
treatment plants
- Biogas storage and use
- Reuse of treated wastewater for irrigation